Question: In a PERT network, the latest ( activity ) start time is the Select one: earliest time that an activity can start without violation of

In a PERT network, the latest (activity) start time is the
Select one:
earliest time that an activity can start without violation of precedence requirements.
latest time that an activity can be finished without delaying the entire project.
latest time that an activity can be started without delaying the entire project.
earliest time that an activity can be finished without delaying the entire project.