Question: In a Project Cost-Duration Graph, total project costs are a sum of direct costs plus interest. direct costs and the project manager's salary. direct and
In a Project Cost-Duration Graph, total project costs are a sum of
direct costs plus interest.
direct costs and the project manager's salary.
direct and indirect costs.
labor, material and equipment costs.
direct labor costs and the project manager's salary.