Question: In a project network, _ _ _ _ _ _ _ _ indicate activity dependency and project flow. Multiple Choice slacks nodes boxes arrows labels

In a project network, ________ indicate activity dependency and project flow.
Multiple Choice
slacks
nodes
boxes
arrows
labels