Question: In a project network diagram, Activity A has an Early Start ( ES ) of Day 1 and an Early Finish ( EF ) of

In a project network diagram, Activity A has an Early Start (ES) of Day 1 and an Early
Finish (EF) of Day 5. Activity B, which is dependent on A, has an Early Start (ES) of
Day 6. What is the total float for Activity B?
a)0 days
b)1 day
c)2 days
d)3 days