Question: In a project to develop an interactive online shopping platform, there were 4 main asks to be done sequentially: 1) Develop specifications: Planned cost $10,000.

In a project to develop an interactive online shopping platform, there were 4 main asks to be done sequentially:

1) Develop specifications: Planned cost $10,000. Planned Schedule 2 weeks.

2) Design platform: Planned cost $30,000. Planned Schedule 4 weeks.

3) Coding and Testing: Planned cost $120,000. Planned Schedule 8 weeks. Training Users, 4)Deployment and Closure: Planned cost $40,000. Planned Schedule weeks.

The first task took 4 weeks to comp..lete and its actual cost was $16.000.




Step by Step Solution

3.45 Rating (161 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To determine the cost performance index CPI and schedule performance index SPI for the first task De... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!