Question: In a project to develop an interactive online shopping platform, there were 4 main asks to be done sequentially: 1) Develop specifications: Planned cost $10,000.
In a project to develop an interactive online shopping platform, there were 4 main asks to be done sequentially:
1) Develop specifications: Planned cost $10,000. Planned Schedule 2 weeks.
2) Design platform: Planned cost $30,000. Planned Schedule 4 weeks.
3) Coding and Testing: Planned cost $120,000. Planned Schedule 8 weeks. Training Users, 4)Deployment and Closure: Planned cost $40,000. Planned Schedule weeks.
The first task took 4 weeks to comp..lete and its actual cost was $16.000.