Question: In a sequential process A - > B - > C - > D in which each step only has a single resource, the bottleneck
In a sequential process ABCD in which each step only has a single resource, the bottleneck of this process is Select all that apply.
a
the activity that has the lowest capacity
b
the activity that has the longest activity time
c
the activity that has the same capacity as the entire processs capacity