Question: In a software development project that is using the Agile development approach, the project team and the product owner are currently engaged in the determination

In a software development project that is using the Agile development approach, the project team and the product owner are currently engaged in the determination of the number of iterations required to produce a finished product and the duration of each iteration based on the business goal, dependencies, and impediments. What process is being carried out in the given scenario? * 1 point Control Schedule. Develop Schedule. Control Quality. Define Scope