Question: In a study, the time (measured or observed time) for a worker to do a job was measured as 5 minutes. The tempo of the

 In a study, the time (measured or observed time) for a

In a study, the time (measured or observed time) for a worker to do a job was measured as 5 minutes. The tempo of the worker was appreciated as 140% and the shares were estimated to be 5%. Calculate the standard time for the activity. Calculate how many pieces of work the worker will do in a working day. TZ=GZDSZ=TZ(1+)SQ=SZT