Question: In a Value Stream you have 3 parallel production lines which supply the assembly line. Assembly line completes the final product. Lead times for the
In a Value Stream you have 3 parallel production lines which supply the assembly line. Assembly line completes the final product. Lead times for the 3 parallel production lines are 65.3 hours, 70 hours, and 92.5 hours, respectively up to the entry point of assembly line. Lead time for the Assembly line is 20 hours. What is overall Lead time for the Value Stream? Cycle time for the 3 parallel production lines up to assembly line is 300 secs, 246 secs and 296 sec, respectively. What is the effective Cycle time for this value stream up to Assembly Line