Question: In a weekly regenerative MRP system, a planned order release (POR) authorized for release in week one, will show up as a scheduled receipt in

In a weekly regenerative MRP system, a planned order release (POR) authorized for release in week one, will show up as a scheduled receipt in the new transaction record generated at the end of week one.Question 16Answera.Falseb.True