Question: In activity-based costing (ABC), costs are allocated into which one of the following? A, Cost groups B. Cost pools C. Cost accounts D. Cost centres.
In activity-based costing (ABC), costs are allocated into which one of the following? A, Cost groups B. Cost pools C. Cost accounts D. Cost centres.
Could you explain the reason as well?? Thanks!