Question: In an activity - based cost management ( ABCM ) system, capacity - related costs are those that are incurred to: Multiple Choice support the

In an activity-based cost management (ABCM) system, capacity-related costs are those that are incurred to:
Multiple Choice
support the research and development process.
cause a change in the engineering plans for a product.
sustain the company's marketing program.
maintain the plant's production capacity.