Question: In an activity network diagram, activity P with a duration of 6 (days) has two immediate predecessor activities where their respective earliest finish times are

In an activity network diagram, activity P with a duration of 6 (days) has two immediate predecessor activities where their respective earliest finish times are 4 and 7. Therefore, the earliest finish time for activity P is:

a. 10

b. 13

c. 17

d. 11

e. 12