Question: In an activity network diagram, activity P with a duration of 6 (days) has two immediate predecessor activities where their respective earliest finish times are
In an activity network diagram, activity P with a duration of 6 (days) has two immediate predecessor activities where their respective earliest finish times are 4 and 7. Therefore, the earliest finish time for activity P is:
a. 10
b. 13
c. 17
d. 11
e. 12