Question: In an activity-based costing system established for assigning overhead costs in a highly automated manufacturing plant, which of the following is true? A. A single,
In an activity-based costing system established for assigning overhead costs in a highly automated manufacturing plant, which of the following is true?
A. A single, plantwide overhead rate is likely to be used
B. Direct labor is likely to be the most important allocation base
C. Multiple activity bases are likely to be selected for overhead allocation
D. A highly automated manufacturing operation does not require overhead allocation