Question: In an agile or adaptive environment, when should risk be monitored and prioritized? a. During each iteration as the project progresses b. Throughout the Planning

In an agile or adaptive environment, when should risk be monitored and prioritized? a. During each iteration as the project progresses b. Throughout the Planning process group and retrospective meeting c. During the Initiation and Planning phases d. Only during the Initiation and Closing phases