Question: In an Agile project, within a ( n ) _ _ _ _ _ _ _ _ _ _ _ , once the replanning is

In an Agile project, within a(n)___________, once the replanning is complete, very little additional change is allowed.
a. knowledge area
b. iteration
c. release
d. process group