Question: In another project there are two activities occurring at the same time with the same duration and requiring resources with the same skills. One activity

In another project there are two activities

In another project there are two activities occurring at the same time with the same duration and requiring resources with the same skills. One activity (called activity A1) has free slack of 10 days while the other one (called activity A2) has a total slack of 10 days, but no free slack. If you needed to take the resources from A1 or A2 to work on an activity on a critical path that was running late would you take the resources from A1 or A2? You must explain your choice. (2 marks)