Question: In Assignment 3, I need help to create a high-level activity list based on the WBS that I completed in Assignment 2 which I attached.

In Assignment 3, I need help to create a high-level activity list based on the WBS that I completed in Assignment 2 which I attached. I also need help making a Project Schedule Network Diagram from the activity list using Word or Excel. Finally, I need help with creating a Gantt Chart Schedule in Word or Excel based on the information that I attached. Assignment 3 is not the complete schedule because the WBS did not decompose the work to the work package level. As project manager, your goal is to provide the big-picture relationship between the activities. Use the template provided and follow the more detailed instructions. I attached the notes and templates from the course that I am taking PRM: 524 Applied Project Management Case

Instructions
Activity Logic
This is an information page. It provides the immediate predecessor to activities.
Use this information to develop the logic diagram
Use the PMI methodology such as starting at week 0 and the week number of the successor is identical to the end week of the immediate predecessor.
Logic Diagram has been started for you.
1. You can continue to use this spreadsheet, just copy and paste the activity boxes according to the logic. Option is to do it another way.
2. Perform the forward pass through the network to determine the early start and early finish of each activity
3. Perform the backward pass through the network to determine the late start and late finish of each activity
4. Calculate the float for activities not on the critical path.
5. Use your calculated start and finish dates to complete the Gantt Schedule on the
6. You don't need add the completed work on the project management plan in the logic diagram. The work is completed.
7. The calculated early start and early finish are correct for the activities shown.
8. Feel free to change the column widths to fit the diagram onto one page.
9. Make a screen shot of your logic diagram to submit as part of the project plan.
Gantt Chart Schedule
1. The activity number and activity description are given.
2. Use the Early Start and Early Finish for the bars on the critical path activities
3. Use the Early Start and Late Finish for activities not on the critical path
4. For the project management activities, use the start date given and end at the end of the project.
5. The monthly progress reports will be completed on four week intervals beginning with the start date given.
6. Move the Milestone Stars in the week in which you achieve the milestone.
7. Make a screen shot of your Gantt Chart Schedule to submit as part of the project plan.
In Assignment 3, I need help to create aIn Assignment 3, I need help to create aIn Assignment 3, I need help to create a
Project Planner Selecta period to highlight at night. A legend describing the charting follows. Period Highligh lan Duration ctual Start % Complete Actual (beyond plan) Complete (beyond plan) PLAN PLAN ACTUAL ACTUAL PERCENT ACTIVITY START DURATION START DURATION COMPLETE Weeks 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 3 100% Milestone Project Charter Approved 5 Project Mgt Docs Phase 1009% I Prepare Req. Trace. Matrix 100% 2 Prepare WB S 3 Prepare Activity Logic Diagram & 10 046 Gantt 2 100% 4 Prepare Budget 100% 5 Prepa 100% Milestone Project Docs Approved Software, Data base Design & 0% Hardware purchase Phase 6 Software Architecture Design 5 09% 7 Proprietary Database Design 0% 8 Open Database link Design 9 Specify Hardware 0% 10 Purchase Hardware Milestone S ware, databases & 0% H'dware Approved Data Exchange & Report Format 0% Phase 11 Bus iness nge to from 0% PMIS 12 Data Exchange tolfrom Open 0% Database 0% 13 Report Format Design Milestone Data Exchange and Report Formats Approved 09% Start up Phase 14 Documentation, Training provided 15 Legacy Data Archived Milestone Docs, Manual, Training 0% and Data Achieve Approved 0% 16 Project Mgt A ctivities 0% 17 Weekly Meetings 5 0% 18 Monthly Progress Reports 09% 19 P ct CloseoutStart Week5 5 9 6 Software Architecture Design LS Float LF 5 7 7 Proprietary Database Design LS Float LF Duration 1. Activity Name Float Key 11 g Specify Hardware LS Float LF 7 10 8 Open Database Link Design LS Float LF Duration 1. Activity Name Float Shading Denotes Critical Path Activities Immediate PLAN PLAN Predecessor ACTIVITY START |DURATION Milestone Project Charter Approved 0 0 Project Mgt Docs Phase Start 1 Prepare Req. Traceability. Matrix 0 1 1 2 Prepare WBS 1 1 2 3 Prepare Activity Logic Diagram & Gantt 2 1 3 4 Prepare Budget 3 1 4 5 Prepare Risk Mgt Plan 4 1 Milestone Project Docs Approved Software, Database Design & Hardware purchase Phase 5 6 Software Architecture Design 5 4 5 7 Proprietary Database Design 2 7 8 Open Database link Design 3 6,8 9 Specify Hardware 1 9 10 Purchase Hardware 3 Milestone S'ware, databases & H'dware Approved Data Exchange & Report Format Phase 10 11 Business Data Exchange to/from PMIS 4 11 12 Data Exchange to/from Open Database 3 11 13 Report Format Design 4 Milestone Data Exchange and Report Formats Approved Start up Phase 14 Documentation, Manual, Prepared Training 12,13 provided 4 11 15 Legacy Data Archived 4 Milestone Docs, Manual, Training and Data Archive Approved None 16 Project Mgt Activities 0 None 17 Weekly Meetings 5 None 18 Monthly Progress Reports 8 14,15 19 Project Closeout 2

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!