Question: In budgeting for contingencies, a project manager would set aside q , for a risk that has a 2 5 % chance of happening with

In budgeting for contingencies, a project manager would set aside q, for a risk that has a 25% chance of happening with a cost od $10,000.
$2500
$5000
$10,000
$25,000