Question: In calculating the probability that a project will be completed within a specified period, based on the PERT analysis, which of the following is a
In calculating the probability that a project will be completed within a specified period, based on the PERT analysis, which of the following is a correct assumption?
a. the actual times are normally distributed.
b. the estimated activity times follow a normal distribution
c. the times along the critical path follows a Student-t distribution
d. the expected completion times follow a normal distribution