Question: In connection with an important contract for a ship, the client requires a high reliability of the ship transport and specifically has requested that the

In connection with an important contract for a

In connection with an important contract for a ship, the client requires a high reliability of the ship transport and specifically has requested that the probability of failure of the power system on the ship must not be higher than 1x10-6 per hour. The shipowner has to perform a risk analysis to show that the system can meet this requirement. What method should be used? Select one alternative: O Event Tree Analysis O Fault Tree Analysis OFMECA O Preliminary Hazard Analysis O Safe Job Analysis