Question: In construction management, how does the 'design - bid - build' delivery method compare to 'design - build' in terms of project timelines? A )

In construction management, how does the 'design-bid-build' delivery method compare to 'design-build' in terms of project timelines?
A) Design-bid-build is faster as it involves more competition
B) Design-build tends to be quicker due to the overlap of design and construction phases
C) There is no difference in project timelines between the two methods
D) Design-bid-build allows for more innovation, thus significantly speeding up the project