Question: In construction scheduling, slack time ( or float ) is calculated as: The difference between the latest and earliest start times of an activity The
In construction scheduling, slack time or float is calculated as:
The difference between the latest and earliest start times of an activity
The difference between the earliest finish time and the earliest start times of an activity
The sum of the durations of all activities in the project
The difference between the actual and planned durations of an activity