Question: In CPM analysis, activities with zero slack: A. lie on a critical path. B. must be completed first. C. can be delayed. D. have no
In CPM analysis, activities with zero slack:
A. lie on a critical path.
B. must be completed first. C. can be delayed. D. have no predecessors