Question: In CPM, if Activity A and Activity B are immediate successors to Activity M then Group of answer choices Activity M cannot start until Activities
In CPM, if Activity A and Activity B are immediate successors to Activity M then
Group of answer choices
Activity M cannot start until Activities A and B are completed
Activity M cannot start until Activities A or B are completed
Activities A and B cannot start until Activity M is completed
Activity A and B must start at the same time
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock