Question: in design bid build the general contractor includes costs for all but the following: 1. Subcontractor costs 2. Project management fees 3. temporary shoring and
in design bid build the general contractor includes costs for all but the following:
1. Subcontractor costs 2. Project management fees 3. temporary shoring and scaffolding costs 4. architectural fees
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock