Question: In Earned Value Management, if a project is over budget and ahead of schedule _ _ _ _ _ _ _ _ _ _ _
In Earned Value Management, if a project is over budget and ahead of schedule
CPI is under and SPI is over
CPI is over and SPI is under
both CPI and SPI are over
both CPI and SPI are under