Question: In Example 2 . 7 , suppose 1 1 machines are to be assigned. Which of the following assignments will minimize the total cost over
In Example suppose machines are to be assigned. Which of the following assignments will minimize the total cost over a common time period: or Is there another combination that will be less expensive?
PRODUCT, PROCESS, AND SCHEDULE DESIGN
Figure Multiple activity chart for Example
Excluding idle time, each machine cycle requires minutes to complete a cycle.
Likewise, the operator devotes minutes to each machine during a cycle. Hence, an
ideal assignment is
For the example, a equals two minutes, equals one minute, and equals six minutes.
Therefore, equals machines.
Since a fractional number of machines cannot be assigned to an operator, consider
what will happen if some integer number of machines, is assigned. The work content
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock