Question: In fast, please Q2: A project manager has a generator construction project that needs to be completed in 1 year and the entire financial plan

In fast, please
Q2: A project manager has a generator construction project that needs to be completed in 1 year and the entire financial plan of this project is $200,000. An evaluation meeting occurred at the beginning of the seventh month. The results of the meeting are that $120,000 have been spent till now and the actual percentage of completion is 40%. However, the schedule indicates that 50% of the work must be finished. Please answer the following questions: 1-How efficiently are we using our time? (5 marks) 2- Will we be ahead or behind schedule? (5 marks) 3- How efficiently are we using our cost? 4- Will we be under or over budget