Question: In February 2 0 2 3 , Crane Construction signed a contract and commenced construction on a parking garage. The total contract price was

In February 2023, Crane Construction signed a contract and commenced construction on a parking garage. The total contract price was \(\$ 91.4\) million and was expected to be completed in July 2025 at a total estimated cost of \(\$ 82.8\) million. Payment by the customer was to be made in several stages, based on significant events and dates throughout the construction timeline. Based on the terms of the contract with the customer, control over the parking garage (i.e. ownership) does not transfer to the customer until completion. Crane's year-end was September 30 and follows ASPE.
By the end of September, 2023, Crane had incurred \(\$ 8,280,000\) in costs and had invoiced \(\$ 9,900,000\) in progress billings. \(\$ 8,200,000\) of the progress billings had been collected.
By September 30,2024, Crane had incurred \$55,230,000 in total costs and had invoiced \$45,400,000 in progress billings, including the progress billings in 2023. Of the total billings, \(\$ 30,500,000\) had been collected. Also, Crane reviewed its cost estimates on the project, and now believed the parking garage would cost \(\$ 78.9\) million in total to complete.
Using the completed-contract method, prepare all journal entries required for the year ended September 30,2023. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts. List all debit entries before credit entries.)
No. Account Titles and Explanation
Debit
Credit
1. Using the completed-contract method, prepare all journal entries required for the year ended September 30,2023. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts. List all debit entries before credit entries.)
No. Account Titles and Explanation
1.
(To record the 2023 cost of construction)
2.
(To record the 2023 progress billings)
3.
(To record the 2023 cash collections) Using the completed-contract method, prepare all journal entries required for the year ended September 30,2024. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts. List all debit entries before credit entries.)
No. Account Titles and Explanation
1.
(To record the 2024 cost of construction)
2.
(To record the 2024 progress billings)
3.
(To record the 2024 cash collections) Prepare the journal entry to record revenue and cost of construction on completion of the project, assuming all billings are completed and the total actual cost is the same as the 2024 estimate. Use Materials, Cash, Payables for costs incurred to date. (Credit account titles are automatically indented when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account titles and enter 0 for the amounts. List all debit entries before credit entries.)
Account Titles and Explanation
Debit
Credit
(To record the 2025 cost of construction)
(To record the 2025 progress billings)
(To record the 2025 cash collections)]
(To record revenue, costs and gross profit of construction of parking garage)
 In February 2023, Crane Construction signed a contract and commenced construction

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Accounting Questions!