Question: In identifying the stakeholders for a project, a project manager would review the organizational chart. The information identified would be documented in the ________. Risk
In identifying the stakeholders for a project, a project manager would review the organizational chart. The information identified would be documented in the ________. Risk register Stakeholder register Communication management plan Stakeholder engagement plan
Step by Step Solution
There are 3 Steps involved in it