Question: In MS Project a user inserts a milestone to indicate progress. What value appears in the new milestone's Duration cell? Question 10 options: 1 day
In MS Project a user inserts a milestone to indicate progress. What value appears in the new milestone's Duration cell?
Question 10 options:
|
| 1 day |
|
| 1 day? |
|
| 0 days |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts