Question: In nonitoring project time ( schedule ) performance, actual performance should be confared to a ) budgets for the current year. b ) top management's

In nonitoring project time (schedule) performance, actual performance should be confared to
a) budgets for the current year.
b) top management's targets
G
c) project network schedule derived from the WBS/OBS.
d) progress on similar past projects.
c) previous status reports.