Question: in operation management Flow Process Measures 4 . Orange Juice Company produces and markets fruit juice. During the orange harvest season, trucks bring oranges from

in operation management Flow Process Measures
4. Orange Juice Company produces and markets fruit juice. During the orange harvest
season, trucks bring oranges from the fields to the processing plant during a workday
that runs from 7a.m. to 6 p.m. On peak days, approximately 10,000 kilograms of oranges
are trucked in per hour. Trucks dump their contents in a holding bin with a storage
capacity of 6000 kilograms. When the bin is full, incoming trucks must wait until it has
sufficient available space. A conveyor moves oranges from the bins to the processing
plant. The plant is configured to deal with an average harvesting day, and maximum
throughput is 8000 kilograms per hour. Assuming that oranges arrive continuously over
time, construct an inventory buildup diagram for Orange Juice Company. In order to
process all the oranges delivered during the day, how long must the plant operate on
peak days? Suppose that each truck holds about 1000 kilograms of oranges, at what
point during the day must a truck first wait before unloading into the storage bin? What is
the maximum amount of time that a truck must wait?

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!