Question: In PERT, what is the probability that a project will be completed within the expected time if the variance of the project s critical path

In PERT, what is the probability that a project will be completed within the expected time if the variance of the projects critical path is 4 and the project has a standard deviation of 2?
68%
50%
99%
95%