Question: In project management, when using the forward and backward pass methods for scheduling, which of the follow a . The backward pass is used to

In project management, when using the forward and backward pass methods for scheduling, which of the follow
a. The backward pass is used to calculate the earliest start and earliest finish times for each activity.
b. The backward pass is used to calculate the latest start and latest finish times for each activity, starting
c. The forward pass is used to calculate the latest start and latest finish times for each activity.
d. The forward pass is used to calculate the earliest start and earliest finish times for each activity.
 In project management, when using the forward and backward pass methods

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!