Question: In regard to resource leveling, why are noncritical path activities generally the first to be delayed? a . Because they are longer in duration b

In regard to resource leveling, why are noncritical path activities generally the first to be delayed?
a. Because they are longer in duration
b. Because they have available slack/float
c. Because they require fewer resources
d. Because they are not important
 In regard to resource leveling, why are noncritical path activities generally