Question: In resource - limited scheduling, the lower priority activities get delayed. How does the delaying of activities affect the project? a . The delaying of

In resource-limited scheduling, the lower priority activities get delayed. How does the delaying of activities affect the project?
a. The delaying of activities decreases the acceptance of the project deliverable.
b. The delaying of activities may delay the project.
c. The delaying of activities increases the costs of the project.
d. The delaying of activities helps give others more time on their tasks because they won't affect the project schedule.