Question: In rolling wave planning, how are subsequent project phases initially planned? Without any initial milestones Based on completed project phases In detailed and specific terms
In rolling wave planning, how are subsequent project phases initially planned?
Without any initial milestones
Based on completed project phases
In detailed and specific terms
At a higher level of abstraction