Question: In Ron Engineering, which statement by Justice Estey is incorrect? The revocability of the offer must be determined: 69 In accordance with the General Conditions
In Ron Engineering, which statement by Justice Estey is incorrect?
"The revocability of the offer must be determined:
69
|
| In accordance with the General Conditions |
|
| In accordance with Information for Tenderers |
|
| Related documents upon which the tender was submitted |
|
| Related documents post bid closing |
|
| All statements are correct. |
Which of the following is not normally applicable to contractor selection for goods?
|
| Invitation to Tender is often used with a public opening. |
|
| There are rated and mandatory criteria. |
|
| Standing Offers are often used. |
|
| Evaluation is based on price. |
|
| Specifications or alternatives are used. |
A statement written regarding the minority opinion in Double N was: 1. the dismissal of the action and third party claim by the courts below not only results in 2. Sureway Construction of Alberta Ltd.s reaping the profits of its deceit, 3. but also enables the City to escape entirely from its implied obligations. 4. Far from preserving the integrity of the tendering process, this result seriously undermines it.
|
| Statement 1 is incorrect |
|
| Statement 2 is incorrect |
|
| Statement 3 is incorrect |
|
| Statement 4 is incorrect |
|
| All statements are correct. |
Which of the following is not one of the four acceptable reasons for sole sourcing in the public sector?
|
| Urgency/emergency. |
|
| Not in the public interest to solicit bids. |
|
| Only one supplier. |
|
| Low dollar value. |
|
| Political necessity. |