Question: In Scrum Process, sprints: a . All mentioned points Ob . can range from 2 to 5 weeks starts with one day for planning and

In Scrum Process, sprints:
a. All mentioned points
Ob. can range from 2 to 5 weeks starts with one day for planning and ends with one day for revision.
O c. have a goal to develop finished functionality that can be reviewed by the produced owner.
Od. while in them, no changes/modification can be made.