Question: In Scrum, work on a product backlog item is complete when: A . It makes it through the sprint review with no objections B .

In Scrum, work on a product backlog item is complete when:
A. It makes it through the sprint review with no objections
B. It receives sign-off by the project manager
C. The Scrum Master considers it shippable
D. It meets the team's "definition of done"
 In Scrum, work on a product backlog item is complete when:

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer