Question: In the carpet city problem, compute a weighted 3 - month moving average forecast for month 4 through month 9 . Assign weights of .

In the carpet city problem, compute a weighted 3-month moving average forecast for month 4 through month 9. Assign weights of .55,.33 and .12 to the months in sequence, starting with the most recent month. According to the result from Excel and/or POM-QM, the forecast for month 4