Question: In the CCPM , after revising a schedule, identifying resource conflicts, and pushing the start dates as late as possible, the project manager starts to
In the CCPM after revising a schedule, identifying resource conflicts, and pushing the start dates as late as possible, the project manager starts to work forward from the start of the project to eliminate sources of conflict.
True
False