Question: In the CM/GC project delivery, which party provides value engineering and constructability input? Group of answer choices Designer Construction Workers Owner CM/GC

In the CM/GC project delivery, which party provides value engineering and constructability input?

Group of answer choices

Designer

Construction Workers

Owner

CM/GC