Question: In the Critical Path Method ( CPM ) with fixed time estimates, what does the critical path represent? The sequence of activities that determine the
In the Critical Path Method CPM with fixed time estimates, what does the critical path represent?
The sequence of activities that determine the earliest completion time of the project
The path with the highest cost
The shortest path through the project network
The sequence of activities that have the most slack time