Question: In the drum - buffer - rope conceptualization used in the theory of constraints, the drum that sets the pace for production refers to: the

In the drum-buffer-rope conceptualization used in the theory of constraints, the "drum" that sets the pace for
production refers to:
the master schedule.
work-in-process inventory before the bottleneck.
first stage in the process.
the bottleneck of the process
total capacity of the process.