Question: In the estimate activity time and cost, using three-point estimates, tE helps define an approximate range for an activitys duration. the expected duration, tE, for
In the estimate activity time and cost, using three-point estimates, tE helps define an approximate range for an activitys duration. the expected duration, tE, for the triangle distribution, can be calculated: a) tE = (2tO+ 2tM+ 2tP) / 4 b) tE = (tO + tM + tP) / 3 c) tE = (3tO+ 3tM + 3tP)/ 9 d) tE = (tO+ tP) /2