Question: In the following figure, the dependency relationship between Test Interface *. .... Design and Amend Documentation is Test Interface Design Amend Documentation 3 days Start-to-Start

In the following figure, the dependency

In the following figure, the dependency relationship between Test Interface *. .... Design and Amend Documentation" is Test Interface Design Amend Documentation 3 days Start-to-Start (SS+3) Start-to-Start (SS) Start-to-Finish Finish-to-Start (FS+3) O