Question: In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction
In the following table the activities with their precedence sequence and expected time (days) are listed for a project on which Carl Betterton's construction company is working: Activity A Immediate Predecessor(s) Time (days) 7 B C E F AAB BCD 4 6 6 4 4 6 E, F 7 G H Carl's team should be able to complete the project in days.